How to make XOG-IN for task and project baseline.

Document ID : KB000124974
Last Modified Date : 21/01/2019
Show Technical Document Details
Question:
I check prj_projects_write.xml and find the following description so that this includes task baseline start date, baseline finish date and baseline workload 

『This project has sample data for all attributes (that can be set through XOG) of task, project Team and assignment』

Then please let me know the way how to make XOG-IN for task and project baseline.
Environment:
PPM 15.4.1
Answer:
You can make XOG-IN for task and project baseline.
But each has the different definition so that please define as follows. 
  Task baseline : <Baselines> tab 
  Project baseline : <ProjectBaselines> tab