Why does a DAILY schedule on the CA 7 CPU JOB SCHEDULING PARAMETER EDIT (DB.2.1-E) screen not honor the ROLL: N (meaning to schedule on non-available days also)?

Document ID : KB000025346
Last Modified Date : 14/02/2018
Show Technical Document Details

Issue:

When using the ROLL: N function on the CA 7 CPU JOB SCHEDULING PARAMETER EDIT (DB.2.1-E) screen, a SCHID should schedule even non-available scheduling days if applicable. However, when using the DAILY option on this screen, the ROLL: N does not work.

Resolution:

When you choose the DAILY option on the DB.2.1-E screen, a schedule is created for the job that matches the calendar used. No non-schedule days are considered. If you want the job to run every day of the week regardless of whether it is available on this calendar, use ROLL: N and a WEEKLY schedule:

 __ X __ WEEKLY    SUN: X  MON: X  TUE: X  WED: X  THU: X  FRI: X  SAT: X