Where we can set the "cost type" for a resource?

Document ID : KB000010085
Last Modified Date : 14/02/2018
Show Technical Document Details
Introduction:

Some people would like to add the attribute "cost type" in different objects.

So we will explain where can be set this attribute.

Environment:
All CA PPM Versions.
Instructions:

The field cost type only can be used in for most investments (included project and idea),It cannot be used for a resource, because a resource can have capital or operating cost, for example in one project it could be operating and in another Capital. 