When using multiple calendars in run_calendar of a job definition, gets message "Job uses Custom calendars, and there are no more days in it!".

Document ID : KB000049755
Last Modified Date : 14/02/2018
Show Technical Document Details

Description:

When using multiple calendars in a job definition in run_calendar, it fails with message:

"Job uses Custom calendars, and there are no more days in it!
THIS JOB WAS NOT SCHEDULED TO RUN!!!"

Needs to associate the same job to different types of calendar: daily, weekly, monthly, yearly.

Solution:

This is working as designed. AutoSys allows providing only one calendar in "run_calendar" section.

In AutoSys 4.5, you may create different instances of the same job, each of them associated with a specific calendar (daily, weekly, monthly, yearly.)

In AutoSys release 11.3 you have the possibility to create complex "extended calendars" which allows the creation of dates with different periods more easily.