When export from PPM to MSP % complete changes his value and vice versa.

Document ID : KB000006166
Last Modified Date : 14/02/2018
Show Technical Document Details
Issue:

MSP and CA PPM are showing different values in % complete field.

Environment:
CA PPM all versions.
Cause:

In MSP you can deactivate task and when are exported to CA PPM, this take as active tasks (PPM does not work with that option).

In PPM shows this task as 0% of percentage completed.

 

 

Resolution:

Delete the task that you don't want to use in MSP instead of deactivate.

Otherwise activate all deactivate task in MSP.