Timesheet Populate and Adjustment Issues with NPIOs in PPM

Document ID : KB000118633
Last Modified Date : 29/10/2018
Show Technical Document Details
Issue:
We are seeing a couple issues with Non Project Investment Objects (NPIOs) such as Other Work on CA Project & Portfolio Management (PPM) timesheets:
  1. Populate button not copying Other Time 
  • We have set our timesheet settings to have the populate button copy entries from the previous timesheet.  It copies tasks correctly but does not copy Other Time.  It doesn’t matter if the Other Time is other work, idea or any other NPIO, the other time line items are not copied to the next week.
       2. Cannot Adjust Other Time
  • When doing a timesheet adjustment the Other Time is not editable.  
Resolution:
Check to make sure the following applies for the impacted project or NPIO:
  • The NPIO is open for time entry and active
  • The effort task associated with the NPIO is open for time entry
Additional Information:
Reference KB000027000 for more details on PPM Timesheet Population - What determines tasks appearing on a timesheet?