The project % complete does not get recalculated when a task is deleted

Document ID : KB000045284
Last Modified Date : 14/02/2018
Show Technical Document Details

Issue:

The Datamart Extraction jobThe project % complete does not get recalculated when a task is deleted

Steps to Reproduce:

1. Create a project and set the % complete method to duration
2. Create two tasks: A and B
3. In task A set the % complete to 50. In task B set it to 10
4. Run the Update % Complete job
5. Check the project % complete field. This has been calculated to 30 (50+10/2)
6. Delete task A
7. Run the Update % Complete job

Expected Result: The project % complete to be calculated as 10%

Actual Result: The project % complete does not get recalculated

Cause:

This is caused by CLRT-80963

Workaround:

Edit task B and click on save and return. The next job run will recalculate the % complete field

Resolution:

This is currently being analyzed by Sustaining Engineering