When a project is saved back from MSP to PPM, when a task is fixed duration and the assignments within the same task are distributed on different time frames, expense and material resource get ETC doubled on the first day.
Steps to Reproduce:
1. Create a Project with a Fixed Duration Task
2. Assign 2 Material or Expense resources to the task, res1 and res2 with loading pattern = Uniform
3. Set 2000 hours ETC for the current month for res1
4. Set 2000 hours ETC for next month for res2
5. Open the project in MSP
Expected Results: res1 has all ETC distributed along the current month, and res2 has all the ETC distributed along the next month
Actual Results: res1 has all ETC distributed along the current month, and res2 has all the ETC distributed along the next month + 2000 hours the first day of the task