Syncing of User Stories from CA Agile Central to CA PPM

Document ID : KB000093202
Last Modified Date : 27/04/2018
Show Technical Document Details
Question:
Why are User Stories from CA Agile Central not syncing into CA PPM?
Environment:
CA PPM version 15.4
Answer:
In version 15.4 of CA PPM, User Stories from CA Agile Central can be synced into CA PPM. But User Stories are synced only if Features are also being synced to PPM.

Following is a scenario where User Stories do not get synced:
1. "PortfolioEpics" (in Agile Central) are mapped to "Projects" (in PPM)
2. "Capabilities" (in Agile Central) are mapped to "Tasks" (in PPM)

However, following is a scenario where User Stories do get synced:
1. "Initiatives" (in Agile Central) are mapped to "Projects" (in PPM)
2. "Features" (in Agile Central) are mapped to "Tasks" (in PPM)

For more about how this functionality works, please refer to the documentation here: https://docops.ca.com/ca-ppm/15-4/en/add-ins-and-integrations/integrate-ca-ppm-with-ca-agile-central.