Question:
What populates the resources who are available on the Assign To field on an Associated Action Item for a Risk, Issue or Change Request? 
Answer:
The resources that are available on the Assign To field on an Associated Action Item for a Risk, Issue or Change Request are those resources who are part of the project participants for that particular project. This is working as designed and cannot be changed. To have additional resources available to select as an action item assignee, those resources would first need to be added as a project participant, they do not necessarily need to be added to the project team as well.