Program Task % Complete is not reflecting Projects % Complete

Document ID : KB000112693
Last Modified Date : 31/08/2018
Show Technical Document Details
Issue:
We have a Program with multiple tasks, on one of the tasks (projects) it shows 0% complete but when we look at that project all tasks are 100% complete. 
Resolution:
% Complete for a project (Example Project A) on the Task list associated with a program is pulled from the project's % Complete value at the project level.

Manual % Complete Calculation Method:
  • If the sub project's % Complete Calculation Method is Manual, this value would be updated manually at the project level (the field is usually on the Schedule subpage). So, in order for the project (Project A) to show up as 100% complete on the program's task list, the project % Complete of the sub project would need to be changed to 100%. 
To update the project % Complete:
1. Go to the project list view in PPM
2. Add '% Complete' to the Project list view
3. Change the % Complete to the desired amount for the sub project (Project A)

Effort or Duration % Complete Calculation Methods:
If you are using Effort or Duration % Complete Calculation Method, then the % Complete would be calculated based on the details listed in the following tech tip:

CA PPM Tuesday Tip: How do the three % Complete Calculation Methods Work

Additional Information:
Reference KB000045739 - When I set the sub project under the program then I cannot change the status of task in sub project.