PPM 15.2.0.213 / SAAS / Timeline dates shift review

Document ID : KB000072659
Last Modified Date : 12/06/2018
Show Technical Document Details
Issue:
I have copied a projet from Production and imported into Dev. I need your help with determining what is causing the dates to adjust in MSP by 2 years from the dates in the PPM Gantt.
Resolution:
Reset the Duration to 'Days' for all new projects in the MSP settings, and then deleted the MSP file from the DB. Also changed the months to days in the lag field and recalculated the number of months as number of days on the problem detail task. This fixed the problem observed in MSP with the project's high-level summary task's Duration and Finish Date.