CA PPM: Planned Cost from Financial Plan Summar does not match Planned Cost on Project Storyboard Report

Document ID : KB000101537
Last Modified Date : 14/06/2018
Show Technical Document Details
Issue:
The Planned Cost on the Project Storyboard report does not match the Planned Cost that is on the Financial Plan Summary on the project in PPM. 

Example:
- Project Financial Plan Summary shows:  
Planned Cost 999,000
Planned Cost Start 4/1/18
Planned Cost Finish 3/29/19

- Project Storyboard report shows:
Planned Cost 910,000 

 
 
Cause:
The Fiscal Time Slices did not cover the range of the Planned Cost.
In this example, the Planned Cost range is 4/1/18 to 3/29/19, but the Fiscal Time Slices have From Date 12/1/15 and Expiration Date 10/1/17. 
Resolution:
1. Update the Fiscal Time Slices so that From Date and Expiration Date cover the Planned Cost date range.
2. Ensure that all 'Monthly' Fiscal Time Periods are Active (Finance -> Setup -> Entities.  Select an entity, click on the Fiscal Time Periods tab)
3. Run job 'Update Report Tables'
4. Run job 'Load Data Warehouse' Full mode
Additional Information:

- Clarity: Time Slice Definition Expiration Date
https://comm.support.ca.com/kb/clarity-time-slice-definition-expiration-date/kb000050490

- CA PPM: Time Slicing Terminology Explanation
https://comm.support.ca.com/kb/CA-PPM-Time-Slicing-Terminology-Explanation/kb000009481

- CA PPM: Time Slice data not being generated
https://comm.support.ca.com/kb/ca-ppm-how-to-reslice-time-slice-ids/kb000022501