Pending Actuals exceeds hours on pending timesheets

Document ID : KB000124299
Last Modified Date : 09/01/2019
Show Technical Document Details
Question:
How are pending actuals calculated for prassignment.prpendactsum?
Answer:
Pending actuals on the assignments are a summation of all the hours for the assignment on ALL open timesheets and then in prpendactsum the number of hours is multiplied for 3600 to show in minutes.

This included timesheet statuses of Open, Submitted, Approved

Once the timesheets post, the pending actual amount decrements accordingly. 

There may be some discrepancies if the timesheet is adjusted as ETC and pending actuals may not update.

Refer to 

KB000052754  Pending actuals are not removed when a task is removed from an un-posted timesheet when the project is overwritten by OWB/MSP.
https://comm.support.ca.com/kb/pending-actuals-are-not-removed-when-a-task-is-removed-from-an-unposted-timesheet-when-the-project-is-overwritten-by-owbmsp/kb000052754



KB000100927  CA PPM: Query to get the pending actuals against a project

https://comm.support.ca.com/kb/query-to-get-the-pending-actuals-against-a-project/kb000100927