Whilst running the Financial Budget and Forecast by Period Detail report from Report and Jobs, the results shows as ‘Undefined’ by group. When the same report is run in Advanced Reporting the correct grouping Is displayed.
STEPS TO REPRODUCE:
1. Navigate to Home > Report and Jobs
2.Select ‘Financial Budget vs Forecast by Period Detail’
3. Fill in the following Parameters;
Investment:
Fiscal Year:
Report Currency:
Financial Plan Group by1:
Financial Plan Group by2:
Expected Result: The selected grouping is displayed
Actual Result: The selected grouping is displayed as ‘Undefined’ (See screenshot below)

4. Navigate to Advanced Reporting > Reports > View List
5. Select ‘Financial Budget vs Forecast by Period Detail’ report
6. Fill in the following parameters with the same information as in PPMInvestment:
Fiscal Year:
Report Currency:
Financial Plan Group by1:
Financial Plan Group by2:
Actual Result: The selected grouping is displayed is displayed correctly (See screenshot below)