Issue:
In Schedule report, the following message is found:

U0011088 Task 'JOBP.NAME' does not start because the scheduled start time lies before the start time of 'JSCH.NAME'
Cause:

The database / AE was restarted after the start time of JSCH, the JOBP which was in the JSCH will not be run if its start time was passed, as:
 
U0011088 Task 'JOBP.NAME' does not start because the scheduled start time lies before the start time of 'JSCH.NAME'
Resolution:
Workaround: run the JOBF manually.
The next run will run normally.