Introduction:
Scheduling Event quarterly at 5pm on the 8th day of February, May, August and November.
Question:
We have a job that is scheduled to run monthly but next scheduled run time is not getting populated?
Event Schedule Criteria;
5PM 8TH DAY FEBRUARY
5PM 8TH DAY MAY
5PM 8TH DAY AUGUST
5PM 8TH DAY NOVEMBER
Environment:
CA Workload Automation DE (dSries)
Answer:
Specify the Event schedule criteria as below, and save the change;
5PM 8TH DAY OF FEBRUARY
5PM 8TH DAY OF MAY
5PM 8TH DAY OF AUGUST
5PM 8TH DAY OF NOVEMBER

Or, simply use;

5PM 8TH DAY OF FEB MAY AUG NOV