Job chain does not display the correct date value

Document ID : KB000086568
Last Modified Date : 14/04/2018
Show Technical Document Details
Issue:
Error Message :
There is no error message

Patch level detected:Univiewer Console 4.0.00
Product Version: Dollar.Universe 6.0.0

Description :When opening a job chain, it displays the 'start date' for all runs. If holds one of the run, then it will display the 'end date' instead.
Environment:
OS: Windows Seven
Cause:
Cause type:
By design
Root Cause: This is a normal behavior of Univiewer Console.
Resolution:
Because there is only one line for the date in the job chain graphic,it was decided to use the end date instead of start date for "Hold" uproc.

Fix Status: No Fix

Additional Information:
Workaround :
N/A