Issue with Other Work Dates in Clarity PPM New UX Timesheets

Document ID : KB000117707
Last Modified Date : 28/02/2019
Show Technical Document Details
Issue:
The other work task end dates on New User Experience (UX) timesheets doesn't match the dates seen in Classic Timesheets or the Other Work Investment Finish Date. 

Steps to where the discrepancy is seen:
  1. Go to New UX timesheets, and click on an open timesheet for a range that covers other work investment timeframe
  2. Click the + Work icon


 
Resolution:
Check the finish date for the team member on the Team tab of the Other Work investment in Classic PPM. The Finish date of the other work item in timesheets pulls from the Team member's finish date versus the Other Work finish date. 
Starting Clarity 15.5 the dates will be completely in sync.