Is there any historical reporting? If so, does it cause any negative impact to the processing of workload when the report is being generated?

Document ID : KB000105688
Last Modified Date : 06/07/2018
Show Technical Document Details
Introduction:
Questions regarding dSeries
Question:
Is there any historical reporting? If so, does it cause any negative impact to the processing of workload when the report is being generated?
Environment:
CA Workload Automation DE
Answer:
The DE scheduler has historical reporting capabilities. It uses a separate java process for reporting so it does not impact the processing of workload. Also, you can move historical data to staging tables and run reports against the stage tables.