Question:
Is there a way to tie specific instance rights to the Resource Manager (RM), that will automatically transfer to a resource when the RM changes?
Answer:
There is no out of the box way to move instance right automatically when RM is changing but as I mentioned I have seen some custom solutions using GEL/XOG where they were removing/adding rights to users and if I am not mistaken they were using audit trail as the mechanism for them to identify when resource manager changed since resource object is not available to be selected to use for process to trigger on update event.