In the MSP New Driver, the Standard Calendar is not respected when a project includes resources using multiple Calendars

Document ID : KB000007061
Last Modified Date : 14/02/2018
Show Technical Document Details
Issue:

When having a project with resources using multiple calendars, the Standard Calendar is not loaded as the Project Calendar in MSP when using the New Driver. 

 

Steps to Reproduce: 

0. In an environment with resources using two calendars (Standard, the actual standard calendar), and another one, with different shift (7.5h), '7.5 Calendar'. 

1. Create a project in PPM 

2. Add resources that have both the 'Standard' (standard) calendar and the '7.5 Calendar' to the project team

3. Create tasks and assign one resource to each task 

4. Open the project in MSP 

5. Check MSP > Project > Properties > Project Information

Expected Results: Calendar shows as 'Standard'

Actual Results: Calendar shows as '7.5 Calendar'

Environment:
CA PPM 14.4 and 15.1
Cause:

Caused by CLRT-80941

Resolution:

This issue is fixed in CA PPM 15.1.0.1 and 15.2.