In the MSP New Driver, % Complete for a Summary Task changes to 0%

Document ID : KB000008682
Last Modified Date : 14/02/2018
Show Technical Document Details
Issue:

In the MSP (Microsoft Project) New Driver, % Complete for a summary task changes to 0% if the child task has a resource assigned and the % Complete is >0 and <100. 

Steps to Reproduce

1. In MSP, create two tasks and make the first task a summary task to the second task
2. Assign a resource to the child task 
3. Update the % Complete of the child task to 50%, which updates the % complete of the summary task to 50% (Issue does not happen if you change the % Complete to 100%) 
4. Save the project back to PPM (% Complete is still correct here) 
5. Export the project to MSP 

Expected Results: Summary task % complete still shows as 50% which matches the child task 
Actual Results: Summary task % Complete is 0% 

Note: If you save the project back to PPM, the % Complete of the summary task is then 0% there. 

Environment:
This issues applies to the MSP New Driver for CA PPM 14.4, 15.1, 15.2, and 15.3
Cause:

This issue is caused by: DE37753 

Resolution:

This issue is currently under review as DE37753