In Clarity on the Work Breakdown Structure (WBS) page the actuals do not match what MSP has, or the total on the Project Dashboard page.

Document ID : KB000053668
Last Modified Date : 14/02/2018
Show Technical Document Details

Description:

Tasks with actuals were changed to milestones in MSP, and then saved back to Clarity. The WBS page does not roll up actuals from milestones to summary tasks.

MSP supports actuals on milestones, but Clarity does not.

Solution:

Open the project in MSP. For any task with actuals and the Milestone field set to Yes, change it to No. Save the project back to Clarity.

In Clarity, if a milestone had an assignment you cannot access the Milestone field, it is not active. The change needs to be made in MSP.