I do not see a project/task on my timesheet. I am unable to post time against a task I am assigned to

Document ID : KB000048108
Last Modified Date : 14/02/2018
Show Technical Document Details

In order to post time against a project, this must be enabled for time entry and the projects track mode must be Clarity.

Please check the Is Open For Time Entry checkbox is enabled at project level.

Make sure the Track Mode is set to Clarity

The project should now be available in your timesheet.

If a specific task is not visible though, please proceed as follows:

  1. Open the specific project
  2. Go to the tasks tab
  3. Open the project in Gantt
  4. Add the Is Open For Time Entry field to the list view.
  5. Expand the work breakdown structure.
  6. Please make sure the task itself and the parent tasks are also opened for time entry. If a parent task is closed for time entry, every child task underneath will also be considered as closed for time entry.