How to XOG OUT Allocation of team staff

Document ID : KB000012621
Last Modified Date : 14/02/2018
Show Technical Document Details
Introduction:

I need to XOG OUT Allocations of team staff.

Question:

Is there any sample XOG OUT xml for Allocations of every team staff?

Answer:

You can use prj_projects_alloc_act_etc_read.xml under <XOG installed directory>/xml. 

 

You will find Resource tag for every staffs in XOG output file. 

For example, defaultAllocation=0.5 means Allocation=50% and defaultAllocation=1 means Allocation=100% .

 

<Resources>
<Resource availFrom="2017-01-05T08:00:00" availTo="2017-01-13T17:00:00" bookingStatus="5" capitalPercentage="0" defaultAllocation="0.5"  isProjectManager="false" lastUpdatedBy="shoichi.sugawara@ca.com" lastUpdatedDate="2017-01-16T12:45:18" openForTimeEntry="true" resourceID="3528195" ......
</Resource>
<Resource availFrom="2017-01-05T08:00:00" availTo="2017-01-13T17:00:00" bookingStatus="5" capitalPercentage="0" defaultAllocation="1" isProjectManager="true" lastUpdatedBy="shoichi.sugawara@ca.com" lastUpdatedDate="2017-01-13T15:34:45" openForTimeEntry="true" resourceID="3754933" ......
</Resources>