How to update Estimate To Complete (ETC) by Pending Estimate automatically in Open Workbench?

Document ID : KB000012857
Last Modified Date : 14/02/2018
Show Technical Document Details
Question:

Is there any function to update value of [Estimate to Complete] by value of [Pending Estimate] in Open Workbench?

Environment:
Open Workbench 2.1.x
Answer:

You can use [Pending Estimates] command in Open Workbench to update value of [Estimate To Complete] by value of [Pending Estimate].

 

 

How to enable [Pending Estimates] command:

 

1. Access to [Customize Quick Access Toolbar] and choose [More Commands…].

s1.jpg

 

2. Choose [Pending Estimates] command from left Commands box and click [Add>>] button.

s2.jpg

 

3. [Pending Estimates] command is added into right box.

s3.jpg

 

4. You will see [Pending Estimates] icon in Quick Access Toolbar.

s4.jpg

 

5. Click [Pending Estimates] icon, then below dialog will pop up.

If select [Accept Pending Estimates], value of [Estimate To Complete]  will be updated by value of [Pending Estimate].

s5.jpg