How to reorder new Tasks in a Project

Document ID : KB000098533
Last Modified Date : 01/06/2018
Show Technical Document Details
Question:
New added tasks will appear by default at the bottom of the list of tasks.
How would it be possible to re-order them according to the Project Plan?
Answer:

The list of tasks for a given project are listed on its Tasks List view
(Project => Tasks tab => Task List)
Project: <Project_Name> - Tasks - Task List

The tasks can be sorted by its displayed attributes on the list (Name, Start, Finish, etc)

To have them ordered as per the project plan, it is possible to use the PPM Gantt Scheduler.
(Open in Scheduler = > PPM Gantt)
This will display the Gantt chart:
Project: <Project_Name> - Gantt,

To have the list of Task reordered:

1. Select the task to be moved.

2. Click on the "Up" arrow button, move.

Task to be moved

3. On the pop up select the Task to which the one selected in Gantt will be inserted before or after.
In this example, Insert Before Task Tarea3

User-added image


The result is the Task being reordered as selected.

Task once is reordered