How to create Estimates (ETC) using XOG

Document ID : KB000055050
Last Modified Date : 14/02/2018
Show Technical Document Details

Description:  
ETC is not created via XOG. After performing the XOG write action, the ETC is not being created automatically in the application.  Is there something I am missing in the XOG input file?

Solution:
You can only XOG in Estimates by using the ETC curve segments.
Under the <Assignments> tag in the <TaskLabor> section you need to specify the ETC segments.


<Assignments>
    <TaskLabor start="2015-03-09T08:00:00" finish="2015-03-27T17:00:00" resourceID="res1">
         <EstCurve>
             <Segment start="2015-03-09T08:00:00"  finish="2015-03-13T17:00:00" sum="40.0"/>
             <Segment start="2015-03-16T08:00:00"  finish="2015-03-18T17:00:00" sum="24.0"/>
             <Segment start="2015-03-23T08:00:00"  finish="2015-03-27T17:00:00" sum="20.0"/>
         </EstCurve>
     </TaskLabor>
</Assignments>