How is Effort Spent calculated in the new User Experience?

Document ID : KB000014953
Last Modified Date : 14/02/2018
Show Technical Document Details
Question:

How is Effort Spent calculated in the new User Experience?

Answer:

Effort Spent is calculated as Project Actuals / (Project Actuals + ETC) x 100.

Additionally, the Investment Allocation job to ensure that effort spent gets updated.

To run the Investment Allocation job:

  1. In PPM, go to Home->Jobs
  2. Click on the Investment Allocation job, then click Submit
Additional Information:

Reference New User Experience: Measure Trends and Publish Project Status Reports for further information on Status Reports in the New User Experience.