Question:
How does Actual Costs get pulled in to Portfolios in Clarity PPM?
Answer:
For the Actual Cost field (column) the data included here is actual cost for the investment that falls within the dates set for the portfolio on properties tab. However, the Actual Cost (Total) and the actual cost in any TSVs would display the totals for the entire project length even if the dates are outside the portfolios.
Additional Information:
SeeĀ CA PPM Tuesday Tip: Portfolio Investment Attributes