How can I enable Auto-Numbering for Task IDs?

Document ID : KB000014902
Last Modified Date : 14/02/2018
Show Technical Document Details
Question:

How can I enable Auto-Numbering for Task IDs?

Answer:

To enable auto-numbering for Task IDs:

1. In PPM go to Administration->Object->Task and click on the the 'ID' attribute on the Attributes tab 
2. Click on the 'Auto-Numbering' tab 
3. Check the check box next to Auto-numbered 
4. Click 'Save'

Notes:

  • To customize the auto-numbering algorithm click the Edit link under 'Scheme'. This includes the ability to add unique letters such as a T, in the beginning of the task ID. 
  • To enable auditing for another object's ID, simply replace "Task" in Step 1 with the desired object. (Example: Project to enable Auto-Numbering for the Project ID field)
  • Note: If you are creating tasks in Microsoft Project (MSP), by current design, the auto-numbering feature is not available. You can enter the Task ID manually in the Text1 field to create a task ID for those tasks. 
Additional Information:

Reference TEC440196 - How to configure Auto-numbering for the Action Item Object

Reference TEC524859 - How can I enable auto-numbering only on one partition and not on System Partition?