Description:
Tasks and milestones are not moving when autoscheduling a master project in the Gantt when at least one subproject is marked inactive.
- Create three projects named, master1, sub1, sub2
- Assign resources to both projects
- Create tasks and milestones on both projects
- Assign resources to the tasks with etc
- Add sub1 and sub2 as subprojects to master1 and mark them read only
- Launch master1 in the Gantt
- Create a tentative schedule with autoschedule
- Note the tasks/milestones shift based on your autoschedule date
- Delete the tentative schedule
- Close the Gantt
- Mark sub1 as inactive
- Launch master1 in the Gantt
- Create a tentative schedule with autoschedule
Expected Result: To see task/ milestone dates change based on your autoschedule date.
Actual Result: No tasks or milestones move in either the master or subprojects.
Solution:
Workaround:
Either mark the inactive subproject as active, or remove it from the master project.
Status:
This has been identified as bug CLRT-71725 which is currently being reviewed by development.
Keywords: SIB, autoschedule, master, project, subproject, active, inactive,CLRT-71725, clarity13open.