[AWA] Forecast doesn’t use Fixed Runtime values

Document ID : KB000115842
Last Modified Date : 26/09/2018
Show Technical Document Details
Question:
What is the Runtime of jobs in forecast if  the Job runtime is set as fixed value in Runtime tab?
Answer:
The forecast always takes the "current ERT" for the forecast calculation. Even if a fixed value is set, this value is used for future executions of the task but not the forecast. If a customer wants to use the fixed value, the ERT calcluation has to be reset first and after the next exeuction, the fixed value is also the "current ERT".