First baseline creation by process is not mark as current revision.

Document ID : KB000008729
Last Modified Date : 14/02/2018
Show Technical Document Details
Issue:

A process is able to create a new baseline revision without marking it current when no existing current revision is present.

Because of that, the baseline is not displaying some baseline information on tasks like  'Baseline Start' and 'Baseline Finish' attributes.

Example:

1)Create a simple process that baselines a project.  The action should be:

a.Baseline the project

b.Create a NEW revision

c.Mark revision ‘current’:  NO

2)Run the process on a project with tasks but NO BASELINES

 

Expect:  Tasks displaying all baseline information.

Actual:  Task is not displaying all baseline information ex ('Baseline Start' and 'Baseline Finish').

 

 

 

 

Environment:
All CA PPM Versions.
Cause:

This is current a defect with the following code: DE37439 

 

 

Resolution:

Mark the baseline created by the process as "current revision" and will correct the display.  

Additional Information:

How is Baseline Usage Calculated?

Document ID:  TEC1997702

https://support.ca.com/us/knowledge-base-articles.TEC1997702.html