Issue:
A long running job fails after the Schedule (JSCH) period turnaround. The JSCH result evaluation is not correct. The status of the failed task is correct in the execution history, but the parent monitor shows an Active status.
Cause:
The behavior is by design. If a task passes the period turnaround, the result evaluation is no longer triggered because the same task is already registered as a new instance.