Extended Calendar Date Adjustments Do Not Follow Non-Workday/Holiday Actions

Document ID : KB000075123
Last Modified Date : 30/03/2018
Show Technical Document Details
Question:
 Why does the date adjustment in an extended calendar not follow the non-workday or holiday actions?
Answer:
The date adjustment in an extended calendar is applied after the non-workday and holiday actions are performed on a date generated by the date condition keyword(s). Therefore, it is possible for the adjustment to shift the generated date to a weekend or holiday as it does not adhere to the non-workday or holiday actions.