Events and summer time change

Document ID : KB000006828
Last Modified Date : 14/02/2018
Show Technical Document Details
Issue:

Since the last summer time change, some applications scheduled to start at 00:15 now start start at at 01:15.

Example of the application having this problem :

 

Event - SCHEDMASTER.ITEM_BULK_RMSMCH_CYCL0060 

Schedule - 00:15 every 2 hours weekdays 

Suspend - 06:17 

Resume - 00:14 

and Do not trigger if active 

Environment:
Dseries versions 11.3 SP3 and 12.x
Cause:

The customer was not using the correct syntax in this context.

Resolution:

You should change the event statement to something like this: 

 

Every 2 hours starting at 00:15. 

 

Here is below the documentation to all the scheduling criteria. 

 

https://docops.ca.com/ca-workload-automation-de/12-0/en/scheduling/schedule-criteria 

 

You will see it has this example: Hourly starting 2 PM today.