Issue:
The command "uxlst tsk full" when launched on an Optional Task does not display the Next Launch as it used to do on version 5. 

Example on version 6 (wrong):
#########################
uxlst tsk ses=134_CCI_HM tsk=* ttype=O full 

TASK SESSION VER UPROC VER MU NATURE START AT END AT PDATE TYPE STATUS CONTROLE USER 
---------------------------------------------------------------- -------------------------------------------------------------------- -------------------------------------------------------------------- --------------------------------------------------------------
TSK(134_CCI_HM)(000)(C_B_CCIHEB)(000) 134_CCI_HM 000 C_B_CCIHEB 000 M1HPCH1 NO MODEL 00/00/0000 00/00/0000 00/00/0000 Optional Enabled appharp
#########################


Example on version 5 (correct) :
#########################
uxlst tsk ses=MACHSES ttype=O full 

SESSION VER UPROC VER MU NATURE START AT END AT DATRAIT NATURE STATUS CONTROLE USER 
------------------------------------------ --------- ------------------------------------------------------------------------------------------- 
MACHSES 000 MACHPRO2 000 MUNIT 12/10/2018 1000 12/10/2018 1100 12/10/2018 Optionnelle universa 
#########################

The same occurs in the UVC - Tasks when displaying the columns "Next Launch", "Next Launch Deadline", "Processing Date" of an Optional Task, the fields are not filled with any value.
UVC - Tasks - Next Launch
Environment:
Dollar Universe 6
Cause:
Next Launch Date was not displayed for Optional Tasks on version 6.
Resolution:
Solution: Update to a fix version listed below or a newer version if available.

Fix version(s): 
Component: Application.Server
Dollar Universe 6.9.61 - Released 15th January 2019