Question:
Can I set a default view in the Task Module in New UI? Is there a way to make it automatically always default to the task list view?
Answer:
When you create a new Project, the Task module will display the last view you used; it remembers the last view you were in. For example: 
- you opened project X, went to Task module, and selected board view; then when you create a new project, in the Task module, the board view is displayed. 
- you opened project X, went to Task module, selected task list view; then when you create a new project, in the Task module, the task list view is displayed. 

You can not set a default view. By design it will display the last view you used.