DCI1112I REMAINING DAYS value does not match the date in LMP key

Document ID : KB000112018
Last Modified Date : 30/08/2018
Show Technical Document Details
Issue:
CA Dynamic Capacity Intelligence (DCI) Controller shows at startup a message indicating that the licence has nnn days remaining.
For example:
DCI1112I: REMAINING DAYS OF LICENSE: 131
Let's assume that 131 days from today is December, 31st 2018  

However the related LMP code has a different date, for example:
CAS9115I - INPUT: PROD(CM) DATE(19OCT19) CPU(nnnn-nnn /ssssss) LMPCODE(*******
CAS9190I - PRODUCT (CM) KEY ACCEPTED FOR THIS CPU

This seems to be inconsistent.
Environment:
CA Dynamic Capacity Intelligence 1.5 GEN 0200
Cause:
zDynaCap (zDC) is installed also on the same LPAR and DCI is looking there for the days remaining in that zDC version.
Resolution:
The DCI1112I was completely removed starting from GEN 0300 as it was misleading. Install all the available maintenance to resolve the problem.