Clarity: Resource Requisition does not hard book when system default 'Allow Mixed Booking' is not checked.

Document ID : KB000052452
Last Modified Date : 14/02/2018
Show Technical Document Details

Description:

Steps to Reproduce:

  1. Make sure Admin Tools > Project Management > Settings > Allow Mixed Booking is not checked.

  2. Create a project.

  3. Add a resource to the team and note the resource is soft booked.

  4. Login in with user with requisition rights and create a requisition for the resource.

  5. Book the requisition.

Expected result: The resource to be hard booked

Actual Result: The resource is still soft booked

Solution:

Workaround:

Manually change the status to hard booked, or if you would like to have mixed booking, then check this option.

Status:

Resolved in Clarity 13.1.0