Clarity: Proposed ETC in v13 is now displaying as 0.00 when null instead of blank

Document ID : KB000021141
Last Modified Date : 14/02/2018
Show Technical Document Details

Description:

Proposed ETC in v13 is now displaying as 0.00 when null instead of blank

Steps to Reproduce:

  1. Log into Clarity v13.0.1 or higher
  2. If you do not have a project create one
  3. In your project add a resource with allocation
  4. This should create the effort task with etc, if not, then create a task and assign the resource
  5. On the Task Assignment view add Proposed ETC
  6. Note to proposed etc displays as 0.00 instead of null
  7. Create a timesheet for the resource and make sure the task displays
  8. Edit the ETC field to 0.00 and save
  9. Note the 0.00 now has a yellow box indicating pending etc
  10. Navigate back to your project and click on the task
  11. View the assignment proposed etc and note it looks the same as before the etc was changed on the timesheet


Expected Result: To be able to see that the assignment now has proposed etc
Actual Result:The 0.00 looks the same as before so the PM does not know the end user request to remove the remaining etc

Solution:

Workaround:
None

Status:
CLRT-70513 is marked as a duplicate to CLRT-72194
CLRT-72194 Resolved in Clarity 13.2