Clarity: PMO Project Storyboard Remaining Allocations does not match Project Team Detail Allocations

Document ID : KB000051023
Last Modified Date : 14/02/2018
Show Technical Document Details

Description:
The PMO Accelerator Project Storyboard Report shows a different value for the Remaining Allocations than what is shown on the Project Team Detail Allocations.
We have checked our Time Slice Definitions and they cover the entire date range of the project.

Steps to Reproduce:

  1. Login to Clarity
  2. Create a project, add team members with non-zero allocations
  3. Execute the PMO Accelerator Project Storyboard Report
  4. Compare the Remaining Allocations value on the report to the value on the Project Team Detail Allocations portlet

Expected Result: Remaining Allocations on the report should match the values on the Project Team Details portlet.
Actual Result: Remaining Allocations on the report do not match the values on the Project Team Details portlet.

Solution:

WORKAROUND:
None. Use the values shown on the Project Team Details Allocations portlet.

STATUS/RESOLUTION:
This issue is only applicable to PMO 2.x
The Project Storyboard Report was re-written for PMO 3.0 and is available now in the CA Clarity Solution Pack (CSP)
Discontinue the use of the old report definition and use the new report definition id = CSP_PRJ_ProjectStoryboard

Keywords: CLARITYKB, PMO-621, pmo20, pmo21, pmo211, pmo22, report content.