Clarity: PMO - How is the Days Late field calculated on the Late Tasks and Milestones portlet? There seems to be situations where a task is not late, but when you look at them on the portlet, it shows as late.

Document ID : KB000052412
Last Modified Date : 14/02/2018
Show Technical Document Details

Description:

The calculation is the task finish date - task baseline finish date.

There is a bug with the NSQL query for the Late Tasks and Milestones. The query is looking at the baseline finish date from the prtask table, instead of the prj_baseline_details table.

Solution:

Status:

Fixed in PMO 1.3

Upgrade to PMO version 1.3. If you cannot upgrade at this time you can XOG in the attached file to fix the NSQL query.

Keywords: CLARITYKB, PMO-278, Late Tasks and Milestones, Days Late, Portlet, pmo11open, pmo12open.