Clarity: Investment Allocation job runs slow

Document ID : KB000021984
Last Modified Date : 14/02/2018
Show Technical Document Details

Description:

Details:

After upgrade to Clarity 12.1.1 the investment allocation job can take considerably longer.

Steps to Recreate:

  1. Install Clarity 12.1.1

  2. Create an other work item (or project) with the following settings: dates 1/1/2010 - 12/31/2030

  3. Allocate some resources to it. This was tested with 25% allocation on the NPIO & 100% allocation on the project.

Expected Result: Investment allocation job to run quickly (seconds).

Actual Result: Investment allocation job takes minutes to complete.

Solution:

Workaround:

  1. If the dates are not set for the NPIO, set the start and end dates for minimal time period as required and the job may run faster.

  2. If the dates are already set previously , the dates can be modified to set them only for the required time period. This may improve the performance marginally.

Status\Resolution:

Resolved in Clarity 13.3

Keywords: CLARITYKB, CLRT-63577, clarity13resolved, clarity133resolved