Clarity: How to create ETC via XOG?

Document ID : KB000053447
Last Modified Date : 14/02/2018
Show Technical Document Details

Description

You can only XOG in ETC by using the curve segments.

Solution

See below an example (XML sample that comes from XOG client installation):

Under assignments in the task labor section, you need to specify the ETC segments,

as in,

   ..............
               <Assignments>
                         <TaskLabor start="2007-09-04T08:00:00"
                                         finish="2007-09-29T17:00:00"
                                         resourceID="res1">
                             <EstCurve>
                                 <Segment start="2007-09-04T08:00:00"
                                               finish="2007-09-29T17:00:00"
                                               sum="100.0"/>
                             </EstCurve>
                         </TaskLabor>
                     </Assignments>
 
 ....................

Keywords: CLARITYKB, xml open gateway, estimate-to-completion, project, slice, curve