Description:

The 'Dependencies' attribute is blank when configured on the Task Gantt Grid

Steps to Reproduce:

  1. Create a Project with Tasks and Dependencies between some tasks
  2. Navigate to Project > Task > Gantt
  3. Configure the Gantt Grid to include the 'Dependencies' attribute

Figure 1

Expected Result: The 'Dependencies' attribute should not be available for configuration on the Task Gantt Grid. It is a virtual, private attribute used in other parts of the application.
Actual Result: The 'Dependencies' attribute is available for configuration and when it is configured, the column cells are blank, empty.

Solution:

Workaround:
None.

Status/Resolution:
Resolved in Clarity 13.0.1 Generic Patch. Reference TEC572268
Resolved in Clarity 13.1.0
When this issue is resolved in a future release, the 'Dependencies' attribute will be removed from the list of available attributes in the configuration.
Task Dependencies can be seen from the Task Gantt visual schedule - position your cursor over the arrows to see the dependency.
Task Dependencies can be seen from the Project > Task > Open a Task > From the Task Properties Tab > Dependencies page.
External Dependencies can be seen from the Project > Dependencies page.