Changing APM Report X Axis Date/Time Format.

Document ID : KB000030773
Last Modified Date : 14/02/2018
Show Technical Document Details

Description:

How to change the X Axis Date/Time for APM Reports.

 

Issue:

An APM graph shows the time in the X axis. It is hard to tell which day of the week it is. How can I switch this to show the date or date/time?

date_time.jpg

 

Solution:

  1. Go to the Management Module Editor

 

  2. If the report template editor is not already open, then open it:

 

      a. With the Management Module Editor open, select the report in the pane on the left.

      b. Click Open Template Editor.  The Report Template appears.  Click on the Display Default Properties Tab.

      c. Scroll down to the X Axis Time Format

 

 X Axis Graph Label 3.jpg

      d. Use the pulldown menu to select the correct format such as Short Date/Time

default.jpg

 3. After saving and running  the report, the report will now have a date/time X axis.

new date time.jpg