Change the start day of the Change Calendar tab

Document ID : KB000004476
Last Modified Date : 14/02/2018
Show Technical Document Details
Issue:

Is it possible to change the start day from Friday(out-of-the box) to Monday or Sunday in the Change Calendar tab by the SDM function?

GW-00083.jpg

Environment:
SDM r14.1
Resolution:

1. Administration tab > Options Manager > Change Order Mgr, and open the chg_calendar_start_day_of_week with edit mode.


2. Select a specific value you want in the Option Value dropdown list box, and click save button.

GW-00085.jpg

 

3. Recycle the SDM service. The indication of the Change Calendar will be changed as follows.

GW-00086.jpg

Additional Information:

Title: Change Order Mgr Options
https://docops.ca.com/ca-service-management/14-1/en/administering/administering-ca-service-desk-manager/options-manager/